All of the customers are now on the new main as of noon Monday, August 18. The
old main was shut off; it will be disconnected on Tuesday. The concrete will be
poured to repair the driveways. Then, all that will remain on the Tell Street
portion is a little cosmetic work, and seeding in another month.
By Thursday, August 21, work will begin on the last portion of the project which
is the short loop to be installed just east of the city shop.